30m³ wet shotcrete mahine usually used for what length of the tunnel

Step-by-Step Calculation

 

1. Shotcrete Volume Per Meter of Tunnel

Example Tunnel Dimensions:

Width: 6 meters

Height: 5 meters

Shotcrete layer thickness: 5 cm (0.05 m)

Tunnel surface area per meter:

Perimeter = (6 + 5) × 2 = 22 meters

Surface area = 22 × 1 = 22 m²

Shotcrete volume per meter = 22 × 0.05 = 1.1 m³

 

2. Tunnel Length Covered Per Hour

Machine capacity = 30 m³/h

Tunnel length covered per hour = 30 ÷ 1.1 ≈ 27 meters per hour

 

3. Tunnel Length Covered Per Day (8-hour shift)

27 meters/hour × 8 hours = 216 meters per day

 

4. Total Length Covered (based on total shotcrete requirement)

If the total shotcrete required is known (e.g., 3,000 m³), then:

3,000 ÷ 30 = 100 hours of spraying

At 8 hours/day → 12-13 working days

At 216 meters/day → ~2,500-3,000 meters of tunnel length

 

Final Answer:

A 30 m³/h wet shotcrete machine can typically cover 200-250 meters of tunnel per day and handle several kilometers of tunnel over weeks of operation, depending on project requirements.

 

Would you like me to adjust calculations for a specific tunnel size or project duration?

 